Suggestion #162
The CR Secretariat Work Plan 2022-2023
Abstract
This is the work plan of CR Secretariat from Aug 1st, 2022 to July 31st, 2023.
Goal
In the coming 12 months, the Secretariat would like to achieve the below goals as follows:
- Transparent status update about the proposals: Track the progress of the proposals and approve their phased payment requests in a transparent way, which will be disclosed in CR Monthly
- Regular update about the proposals to the Council: Regularly update on the status of the active proposals that are approved by CRC to the Council at a quarterly basis
- Build the communication channel for Council members: Host Council Meetings on a biweekly basis (excluding national holidays)
- Professional social media management
- 12 CR Monthly reports(EN) and 12 CR Monthly reports(CN) which will be released on CR website
- Transparent financial update about CR Treasury: 2 CR Financial reports which will be released on CR website
- Announcements/blogs with regards to CRC which will be released on CR website
Motivation
As a subsidiary body of the CR Council, the CR Secretariat's main purpose is to support the operations of the CRC, which includes providing necessary support for the Council to reach CRC, and executing the CRC of the Council.
The CR council is established to reach the CR consensus. The CR Secretariat is the team to execute the CR consensus. This work plan describes the responsibility of the CR Secretariat to ensure a healthy and transparent implementation of the CRC in the coming year.
Plan introduction
The CR Secretariat would focus on the following tasks as listed below:
- Proposal follow-up
Proposal follow-up: It is the first and foremost task for the CR Secretariat to implement the proposal follow-up processes to maintain a healthy and thriving CRC mechanism. As for each proposal approved by CRC, the Secretariat shall review deliverables/related financial records and approve/reject staged payment requests to track the proper execution of the proposal.
I would strongly suggest all CR Council members pay more attention to completion payments and checkpoints when reviewing the proposals. Completion payments and checkpoints defined in the proposals enable the CR Secretariat to efficiently track progress of the proposals.
- Facilitate internal communication among the Council members and the communication between the Council and non-Council members
“Communication leads to community, that is, to understanding, intimacy and mutual valuing”. I am a true believer in the power of communication. As the Secretariat did last year, we will continue to facilitate both the internal communications within the Council and other communications between the Council members and Elastos community.
- CR social media management
Last year, the Secretariat reactivated the CR Twitter account. We plan to continue to manage Twitter in this workplan.
- CR monthly update (CN and EN)
To present the dynamics of the CRC and the proposals funded by the CR, the CR Secretariat will be responsible for publishing CR Monthly at the end of each month, which includes updates about CR Council motions and CR-funded proposals, or any other information that may be disclosed with the permission of CR Council. The CR Monthly Update delivers more transparency in terms of the execution of CRC.
- CR Financial update (CN and EN)
The CR Financial update will provide an update about how the funding in CR Treasure is allocated for approved proposals every 6 months.
-
CR announcements/notifications/blogs with regards to the CRC and the Council
-
Necessary involvement with some proposals with regards to
-
Community questions relating to the Council and CRC
Questions relating to the Council and CRC: As usual, if you have any questions relating to the CRC and the Council, please reach out to the Secretariat at [email removed].
Budget introduction
-
All unspent budget will be returned to CR at the end of the service year. The amount of ELA applied for in this proposal is calculated using 75% of the current ELA price (1ELA=$1.35). This method is to improve work efficiency and avoid a second budget proposal due to price fluctuations.
-
As per the previous work plan, we have returned 8679 ELA back to the CR Treasury (Total ELA applied:34,400)at the end of the first and second work quarter. We will conduct the last review for our financial record around July 31st of 2022 when the Secretariat fulfills the responsibilities for our 4th service quarter.
-
Given the Secretariat is likely short of budget for July due to the low value of ELA, It is estimated that about 3000 USDT budget from the current work plan would be used for the operating cost in July.
-
The above budget is based on the following assumption: There are no more than 30 proposals funded by CR within the next 12 months. If this number is exceeded, the CR Secretariat will submit a second budget proposal.
-
Given that this work plan expands the scope of our work comparing to the previous work plan and also the world-wide inflation has happened,it is expected to increse the operating cost of the Secretariat by 30% when ELA price exceeds $2.0. When ELA price goes below $1.00, the Secretariat shall submit a new budget propsoal if necessary.
- Social media management: 500 USDT
- CR Monthly CN & EN (writer, editor, translator):estimated at 1500 per month
- CR Fiancial reports/CR announcements CN & EN (writer, editor, translator): estimated at 1000 USDT per month
- Technical advisory/Necessary participation in some proposals: estimated at 1000 USDT per month
- Secretariat Management/Proposal tracking/other Secretariat operating matters: 2000 USDT per month
- Buffer fund for 1), 2) and 3) (about 20 percent): 1000 USD in ELA per month
Total estimate: 84000 USDT (84000 ELA)
Budget amount
84000
Plan
| Milestone goal | Date |
|---|---|
Fulfill the tasks defined in the workplan | 2022-09-01T05:00:00.000Z |
Fulfill the tasks defined in the workplan | 2022-10-01T05:00:00.000Z |
Fulfill the tasks defined in the workplan | 2022-11-01T05:00:00.000Z |
Fulfill the tasks defined in the workplan | 2022-12-01T06:00:00.000Z |
Fulfill the tasks defined in the work plan | 2023-01-01T06:00:00.961Z |
Fulfill the tasks defined in the work plan | 2023-02-01T06:00:00.961Z |
Fulfill the tasks defined in the workplan | 2023-03-01T23:14:09.628Z |
Fulfill the tasks defined in the workplan | 2023-04-01T22:14:09.628Z |
Fulfill the tasks defined in the workplan | 2023-05-01T22:14:09.628Z |
Fulfill the tasks defined in the workplan | 2023-06-01T22:14:09.628Z |
Fulfill the tasks defined in the workplan | 2023-07-01T22:14:09.628Z |
Fulfill the tasks defined in the workplan | 2023-08-01T22:14:09.628Z |
Budget
| Type | Milestone | Amount | Criteria |
|---|---|---|---|
ADVANCE | 0 | 7000 | Start to work on the tasks defined in the workplan. |
CONDITIONED | 1 | 7000 | Fulfill the tasks defined in the workplan |
CONDITIONED | 2 | 7000 | Fulfill the tasks defined in the workplan |
CONDITIONED | 3 | 7000 | Fullfill the tasks in the work plan |
CONDITIONED | 4 | 7000 | Fulfill the tasks defined in the work plan |
CONDITIONED | 5 | 7000 | Fulfill the tasks defined in the work plan |
CONDITIONED | 6 | 7000 | Fulfill the tasks defined in the workplan |
CONDITIONED | 7 | 7000 | Fulfill the tasks defined in the workplan |
CONDITIONED | 8 | 7000 | Fulfill the tasks defined in the workplan |
CONDITIONED | 9 | 7000 | Fulfill the tasks defined in the workplan |
CONDITIONED | 10 | 7000 | Fulfill the tasks defined in the workplan |
COMPLETION | 11 | 7000 | Fulfill the tasks defined in the workplan |