Council Nodes Hardware Upgrade Proposal

状态

第 1 步,共 3 步下一步:提出

为什么是这个状态?

  1. 1. 发布当前
  2. 2. 提出尚未开始
  3. 3. 决定尚未开始

Abstract

A recent outage on Elastos ECO chain run by Council members showed that nodes using shared CPUs are not strong enough for current traffic across Main Chain, ECO Chain, ESC, EID, oracles, and Cross-chain Arbiters. This proposal requests funding to replace Council servers that run on shared CPUs with dedicated-CPU machines from OVH, Hetzner, and InterServer, distributed across regions and vendors to avoid a single point of failure. Target start is October 1 and completion by October 15.

Goal

Upgrade majority of Council nodes now on shared CPUs to dedicated servers, keep the network stable during migration, and reach 99.9 percent monthly uptime.
Plan:

  • Providers: 3 different providers.
  • Distribution: multiple regions, no single provider hosts more than one quarter of Council roles.
  • Ownership: each server is owned by the council member. Neither Infinity nor DAO secratary will have ownership rights over the servers.

Motivation

  • Shared CPU plans throttle under load, which risks block lag, chain downtime, and cross-chain Arbiter instability.
  • Dedicated CPUs with consistent IOPS and network throughput raise headroom for traffic spikes.
  • Spreading nodes across multiple providers and regions cuts correlated risk.

Plan introduction

Each server will have at least 8 dedicated vCPUs, 32 GB RAM, and 300 GB of NVMe storage.

Infinity Team will get the plans specified from the server providers (name of the server providers will be hidden to public for chain security measures), match roles to regions and providers, help all council members with technical assistance and make sure all council members install the software properly. We will migrate one by one when height is in sync, and quality assured.

The 12-month total is expected to stay under 10,000 USD. We request 11,000 USDT as a buffer, any extra goes back to the DAO treasury. Funds are requested from the DAO multisig, to be sent to: 0xe02ca89eedb1f83ca0c0155cc84729e125bf8bad

The DAO Secretariat and Infinity Team will plan and send payments to each Council member, help them pick the right plan for their role, and provide hands-on technical help during setup and cutover.

From October 1 to October 5 Council members will buy the servers, build them, and bring baseline monitoring online. From October 6 to October 12 we migrate in stages and run tests. From October 13 to October 15 we run final checks and completely migrate.

Plan

Milestone goalDate

Help council nodes get the servers and start installing the software.

2025-10-02T02:02:46.181Z