建议

建议 #60

Budget request for CR website development for Q3,Q4 of 2020

状态

第 1 步,共 3 步下一步:提出

为什么是这个状态?

  1. 1. 发布当前
  2. 2. 提出尚未开始
  3. 3. 决定尚未开始

Abstract

本提案旨在为CR网站(www.cyberrepublic.org)项目申请2020年Q3及Q4开发,运营维护费用。 CR网站从2019年初改版,最初的设想是提供一个社区自发提交意见,由代理人投票来体现社区自治意愿的平台。目前CR网站在持续开发中,前期申请经费已经花完。现通过此提案,提出CR网站下阶段开发目标及费用申请。

This suggestion is to apply for the budget for CR website(www.cyberrepublic.org) development, operation and maintenance. CR website serves as a platform for Elastos community to raise opinions freely, for the CR council members to vote on the proposals, thus achieving self-governance of Elastos community. Right now, the CR website is under continued development. We have run out of our budget, so we would like to ask for fund for the future development and maintenance of CR website.

Goal

Goal of Q3 and Q4,2020
-当前,所有的提案原文还是存储在CR网站的后台服务器上,只有hash上链,那么下一步,为了更彻底的去中心化,所有提案将全部原文上链,这样即使CR后台服务器关掉,所有的CR提案原文仍然可以从链上获取,任何客户端都可以从链上获取并显示提案信息。
-支持新的提案类型,比如DID短域名的预留及撤销提案,一旦CR共识通过,亦来云区块链代码将自动执行。
-持续的bug fixing和优化改进

-Right now, the full contents of proposals are stored in CR backend server centrally, only hash of proposals are stored on-chain. So in next major release, the original contents of proposals will be fully stored in Elastos blockchain. As a result, even if the CR website is offline, the contents of proposals can be accessed and shown by any clients.
-Support new proposal types. eg. the reservation and un-reservation of DID short name. Once the proposal reaches CR concensus, the implementation will be carried out Elastos Blockchain code automatically.
-Continued bug-fixing and improvements.

Motivation

CRC,既CR共识,是亦来云继PoW和DPoS之后的第三种共识,其目的是为CR提供一种基于共识的社区治理机制,以持续推动亦来云技术开发和生态发展,解决争议,管理社区资产,激励社区成员参与社区的治理和贡献。从CRC委员选举开始,到提案的发起、推荐,投票表决和执行跟踪,所有参与共识的个体行为都通过亦来云主链的交易进行。 社区成员可以很方便地通过支持CRC的客户端参与并监督共识进展。CR网站和亦来云钱包均属于支持CRC的客户端,都是CRC的重要环节,分别承担不同侧重的功能。

除此之外,CR社区成长初期,需要这样的网站作为相对集中的社区交流平台,交流和分享Elastos Smartweb技术知识,共商生态发展,社区自治。

The Cyber Republic Consensus is the third Elastos consensus mechanism after PoW and DPoS. The purpose of CRC is to provide a consensus-based community governance mechanism that will drive Elastos’ technological and ecosystem development, dispute resolution, and management of community assets, and establish incentives to foster community participation in the governance of and contribution to the Elastos community.

All the actions around CR Consensus are to be stored in Elastos Blockchain and reflected in CRC Clients. CR Website and ELA wallet are both applications supporting CR Consensus and follow the interface specifications of CRC in the Elastos Blockchain.

Other than this, in the very beginning of Cyber Republic, there is a strong need of such a platform where community can share and exchanges ideas, suggestions to collectively develop Elastos technology and ecosystem.

Plan introduction

CR网站的产品定义,设计,开发都由亦来云社区开发人员完成,主要以完成CR共识白皮书里定义的功能,和ELA Wallet和亦来云区块链对接,共同实现CR共识,同时根据社区对于网站的反馈,进行改进和优化,。 网站的开发主要包括网站前端,后端服务器,数据库开发,与亦来云主链,DID侧链的对接。一般情况下,每个月会发布一个更新版本。

The design, development of CR website are implemented by Elastos community developers. The main goal is to implement the CR consensus defined in CRC whitepaper, integrate with ELA Wallet and Elastos mainchain, DID chain. The team also collects feedback from community, CR council member and take actions. Normally CR website releases new versions every month.

Budget introduction

每个月由工程师填报工作量,由产品经理和项目经理审核通过后,发放奖励。前一次向CR申请的开发费用在付完团队7月份工资后消耗完毕。因此现申请CR网站开发团队从8月份至12月份的开发费用,申请到的费用如果没有用完,会用于下一个阶段的开发,如果实际费用超出预算,将再次向CR委员会申请,并提出充足理由。所有的费用支出都记录在: https://docs.google.com/spreadsheets/d/1kj-ItSmWlURYtmNvphgipOr0_jArpJj09vjPIgr6XZM/edit#gid=0 (opens in a new tab)

前期费用申请相关提案如下:
CR Interrim Council Stage Proposal #57:https://www.cyberrepublic.org/proposals/5c406167724ac30089847c73 (opens in a new tab)
CR Interrim Council Stage Proposal #150:https://www.cyberrepublic.org/proposals/5df224bbab0cad007830a2a7 (opens in a new tab)
CR Interrim Council Stage Proposal #177: https://www.cyberrepublic.org/proposals/5eabd8e9e604630078922486 (opens in a new tab)
根据历史数据,CR开发每个月的费用(包含一名产品经理,两名开发,一名测试,兼职设计工程师)在1.5万美金左右,因此,此次拟申请75,000美金,以火币ELA/USDT MA30 为1.5计算,申请50,000 ELA

At the end of every month, the developers will submit their timesheet and the project manager will check whether the timesheet is reasonable and appropriate. The reward will be distributed based on their contribution and proof of work. In previous proposal, we applied budget until Q2, 2020. The budget is nearly used up after the July reward was distributed. So in this proposal we would like to ask for the budget for Aug, Sep, Oct, Nov and Dec. In the case the budget is left over after Dec, we will use the remainings for the future development. All the expenditure is logged in https://docs.google.com/spreadsheets/d/1kj-ItSmWlURYtmNvphgipOr0_jArpJj09vjPIgr6XZM/edit#gid=0 (opens in a new tab) accessible upon request.

The relevant proposals are listed below:
CR Interrim Council Stage Proposal #57:https://www.cyberrepublic.org/proposals/5c406167724ac30089847c73 (opens in a new tab)
CR Interrim Council Stage Proposal #150:https://www.cyberrepublic.org/proposals/5df224bbab0cad007830a2a7 (opens in a new tab)
CR Interrim Council Stage Proposal #177: https://www.cyberrepublic.org/proposals/5eabd8e9e604630078922486 (opens in a new tab)

The average monthly development cost including one product manager, two developers, one tester and a part-time designer is abour 15k USD. Thus, here we would like to aks for 750k USD for 5 months. Using the ELA/USDT MA 30 day price, which is 1.5, we would like to ask for 50,000 ELA.

Budget amount

50000

Plan

Milestone goalDate

Q3 Release

2020-09-30T12:58:46.551Z

Q4 Release

2020-12-31T12:59:00.556Z

Budget

TypeMilestoneAmountCriteria

ADVANCE

0

50000

用于支付8月至12月开发费用

COMPLETION

1

0

尾款

登录后可另存为草稿 将创建一份私人草稿,保存之前不会存储任何内容。

回到顶部

语言